TopIntroduction
The Motor Transport Program Office for the U.S. Marine Corps Light Tactical Wheeled Vehicle (TWV) fleet makes decisions each year concerning the timing of new procurements, inspections and repair only as necessary (IROAN), existing fleet overhauls contributing to service life extension programs (SLEP), and end-of-service retirements on all of the vehicles in their fleet. Because of the dynamic nature of vehicle life-cycle management and ever-changing budgetary and policy constraints, any decision support model needs to have the flexibility to run a broad range of quick-turn course-of-action (COA) excursions and “what if” drills on a host of parameters that drive both of the underlying cost and value return models.
Included among the varying assumptions and conditions is a definition of what is ‘best’ for a set of scenarios. For example, during one excursion ‘best’ may mean meeting fleet sustainment requirements at the lowest possible life cycle cost to the Marine Corps, while in another it may mean maximizing troop protection while meeting other requirements and possibly flexing on budget limits. As shown in the workflow of Figure 1, supporting cost and value models were developed in a coordinated, parallel effort as part of the overall project. The multiple objective decision analysis (MODA) based value model (Keeney & Raiffa, 1993; Keeney, 2008; Parnell et al., 2010) assesses the military effectiveness of each COA, complementing the life cycle cost models (Dhillon, 2010) that estimate associated COA cost burdens. These cost burdens represent projections for a fifteen year planning horizon associated with maintaining vehicles over their remaining useful life, availability of the suite of new vehicles, and various budgetary considerations within and external to the organization (USMCLC, 2008).
Figure 1. Flow of modeling elements
The cost model populates the network optimization model with procurement (PCM) and operations and support (O&S) coefficients for maintaining each vehicle type. These costs included annual and event-based costs comprised of Inspect and Repair Only as Necessary (IROAN), Service Life Extension Program (SLEP), and Procurement activities. These estimates represent one-time costs to procure or overhaul a vehicle in any year.
O&S costs are annualized and include the per vehicle cost for fuel, consumables, and repairs. Annual costs are driven by vehicle age instead of being organized relative to a fiscal year. Since HMMWV A2s have been fielded since 1995, and the ECVs since 2004, data related to procurement and maintenance of these vehicles has been well established. Procurement, SLEP, IROAN, and annual O&S costs have been forecasted for developmental systems ECV II and JLTV based on the costs and performance metrics of analogous existing systems. The overall cost estimation methodology is shown in Figure 2.
Figure 2. Life cycle cost estimating methodology
In a similar practice as the U.S. Army Tank-Automotive Command (TACOM) previously imposed (Seng, 2007), the Program Office required any resulting analytical models to remain within the capabilities of standard desktop software (i.e., Excel with Premium Solver) primarily for rapid ‘what if?’ explorations, transparency, ease of future in-house modifications, and budgetary reasons. While understandable, this requirement generally ruled out adopting more computationally taxing or sophisticated approaches employed in maintenance and replacement scheduling such as genetic algorithms (Maji, 2007), dynamic programming (Hsu et al., 2011), integer programming (Stasko & Gao, 2010), ant colony optimization (Abrahão & Gualda, 2006), integrated analytic hierarchy and genetic algorithms (Wang et al., 2006), two-phase Benders decomposition (Wu et al., 2005), and backwards allocation algorithms (Joo, 2007) whose computationally demanding yet efficient algorithms could be used to pursue discrete, exact solutions rather than relaxations.